Track Record

Tobago Case Study

(view Caribscope Video)

  • Robert Bisson and EarthWater’s success on the island of Tobago illustrates the significant implications of Megawatershed exploration and development
  • In the year 2000 Tobago was in the midst of a severe water crisis that threatened to discourage foreign investment and impede economic growth
  • The Island had a computed water supply deficit of 2 to 3 MGDs (roughly 35% of total water demand). During both dry and wet seasons, the Island’s water supply deficit effectively double
  • The Government of Tobago considered several options:
    1. Damming the Richmond River to create a reservoir
    2. Groundwater Development
    3. Seawater Desalination
    4. Water Barging (importing water from elsewhere, specifically the North Coast of Trinidad)
    5. Upgrading existing water treatment plants

(Options 3 - 5 were deemed too costly and / or environmentally harmful. Option 1 was initially chosen, even though it would destroy a portion of a protected rainforest in Northern Tobago)

In June 1999, experts from the Dutch consulting firm Delft Hydraulics completed a technical report for Tobago’s government that indicated significant, additional groundwater could not be developed in either Tobago or Trinidad. For decades expert geologists, both local and foreign, had concluded that Tobago’s “incremental” groundwater supply was limited to 0.5 MGDs, half of which was already being accessed. The most viable option to achieve the 5 MGDs goal appeared to be damming the Richmond River; building the dam would have taken eight years, cost $60 to $80 million (excluding the requisite infrastructure, roads, pumps, etc.) and would have destroyed a portion of the Island’s rain forest.

In a final attempt to avoid constructing the dam, Tobago contracted EarthWater to employ its groundwater exploration and development approach; EarthWater targeted high-yield wells in the Island’s underlying bedrock as new sources of freshwater and chose locations proximate to Tobago’s existing water existing distribution system.

EarthWater Results:

  • Within one year EarthWater had not only developed the amount of water the dam was expected to supply but also discovered 10x that amount; 5 MGDs of sustainable groundwater were developed and a total of 50 MGDs were discovered (an amount 100x previous groundwater estimates)
  • The Megawatershed model was employed for 1/30th of the projected cost of the dam with virtually no environmental consequences
  • EarthWater's work enabled economic expansion and encouraged foreign investment capital, one notable example being the completion and opening of a U.S.$100 million Hilton Hotel development that had previously been delayed due to water constraints

Trinidad Contract (2002-2003): EarthWater went on to perform a similar at-risk contract in Trinidad, where 20 MGDs was developed and > 250 MGDs was identified for future development

Picture at right: Robert Bisson, EarthWater's President, toasts a successful project with President Robinson of Trinidad and Tobago